SlideShare a Scribd company logo
1 of 14
Download to read offline
PUBLIC BRIEFING ON
LYNAS LANTHANIDES PROJECT


          PRESENTER :
PUAN AZURI AZIZAH BT. HJ. SAEDON


  DEPARTMENT OF ENVIRONMENT PAHANG
         TINGKAT 4, BANGUNAN ASIA LIFE
                     JALAN TELUK SISEK
                         25662 KUANTAN
Department of Environment

                          Ministry of Natural Resources
                                  and Environment




       Other government         Department of             Other government
           agencies           Environment (DOE)               agencies




       1975 - Environment Division
       1983 - Department of Environment (DOE)




                                       -2-
Roles of Department of Environment (DOE)
   To administer and enforce the Environmental Quality
   Act, 1974 :
     Prevention, abatement and control of pollution and
     enhancement of the environment
   There are 34 subsidiary legislations under the Act




                           -3-
Lynas must comply to the following Act &
Regulations
   Environmental Quality Act 1974 :
       Environmental Impact Assessment (EIA) report
       Quantitative Risk Assessment (QRA) report
   Guidelines for Prevention and Control of Soil Erosion and
   Siltation in Malaysia , October 1996.
   Environmental Quality (Sewage, and Industrial Effluents)
   Regulations, 1979
   Environmental Quality (Clean Air) Regulations,1978
   Environmental Quality (Scheduled Wastes) Regulations, 2005
   Planning Guidelines for Environmental Noise Limit and Controls,
   2004



                                -4-
Conditions of Approval for Lynas
   EIA and QRA prepared by registered environmental consultant
   Proper and designated drainage system for the Residue Storage
   Facilities (RSF)
   Safety and Emergency control
   AELB’s approval on monitoring, management and disposal of
   radioactive containing materials
   Chemical and scheduled waste management
   Solid waste management
   Environmental management plan (EMP)
   Control and monitoring of :
       Air quality      - soil condition       - Noise
       Water quality including underground water


                                 -5-
Requirements that Lynas must comply and monitored
by DOE
   Suspended solid less than 100 mg/l from the silt trap discharge
   during construction
   Water quality monitoring report on 30 parameters upstream and
   downstream of Sungai Balok
   4 borewells for underground water quality monitoring
   Ambient Air Quality monitoring of parameters CO2, CO, NO2, NO,
   SO2, HF, H2SO4, PM10, and TSP
   Noise monitoring at four (4) stations
   Discharge effluent quality report from the final discharge point
   Stack emission sampling to comply Standard C, Clean Air
   Regulations, 1978 and AELB’s standards.
   Compliance report
   Environment audit report



                                 -6-
Lynas Project : AIR
How will Lynas ensure its Air Emissions meet DOE requirements?

     Lynas will install waste gas treatment systems for the removal
     of sulfuric acid and sulfur dioxide
     It is a five-stage waste gas scrubbing system
     Lynas also has an emergency scrubbing system to ensure air
     emission meet DOE requirements at all times
     Air Quality Modelling has been completed




                                  -7-
Lynas Project : WATER
How will Lynas ensure its Industrial Effluents meet DOE requirements?
     Lynas will install a 2-stage waste water treatment system
        High Density Sludge Neutralization
           to neutralize acids and remove metals
        Industrial effluent treatment system (IETS),
           an activated sludge bio-treatment
           To treat process water to reduce BOD and COD
           IE discharges to comply to Standard B of Regulation 8(1)(b),
           Environmental Quality (Sewage, and Industrial Effluents) Regulations,
           1979 and AELB’s standards

     Lynas will install an independent storm water system
        To ensure Storm water will not be contaminated by process water
     Waste water from the Water Leached Process is recycled back
     to the process.



                                      -8-
Conclusion
   DOE approved the Lynas Project after a detailed review of the
   EIA and QRA submitted by Environ in Jan 2008. Approval was
   granted with conditions in Feb 2008.
   DOE separately approve the detailed design of key pollution
   control equipment prior to installation, and for the Lynas
   Project this includes the waste water treatment plant and the
   waste gas treatment plant.
   After EMP approval on Dec 2008, three site visits have been
   conducted by DOE; construction works complied to EIA
   conditions.
   DOE, as the regulator, will ensure that Lynas operates
   consistent with the act and regulations so that the impact to
   the environment is minimised.




                               -9-
Thank you
Water Quality Monitoring


               W7




              W6


               W5




                    W4

                    W3




                           W2


                           W1

                                -11-
Underground Water Quality Monitoring

                                      S3
                                           S1




                S7
                                           S2
                     S4

           S6



                          S5




                               -12-
Ambient Air Quality Monitoring


         A3                              A1




                                    A2


              A4




                             -13-
Noise Monitoring


         N3                    N1




                          N2
              N4




                   -14-

More Related Content

What's hot

Brad Shultz, OSMRE, “Effective Aerobic Wetland Design for Metals Polishing in...
Brad Shultz, OSMRE, “Effective Aerobic Wetland Design for Metals Polishing in...Brad Shultz, OSMRE, “Effective Aerobic Wetland Design for Metals Polishing in...
Brad Shultz, OSMRE, “Effective Aerobic Wetland Design for Metals Polishing in...Michael Hewitt, GISP
 
Doug Deason - Annual Meeting
Doug Deason - Annual MeetingDoug Deason - Annual Meeting
Doug Deason - Annual MeetingAIPRO
 
Leed Water Efficiency Credits V3
Leed   Water Efficiency Credits  V3Leed   Water Efficiency Credits  V3
Leed Water Efficiency Credits V3NazarethTankarian
 
M. pinto n8848489 project 1_presentation
M. pinto n8848489 project 1_presentationM. pinto n8848489 project 1_presentation
M. pinto n8848489 project 1_presentationMpin2
 
Dr. Abdul Rehman Khan - Rehabilitation of an industrial mercury contaminated ...
Dr. Abdul Rehman Khan - Rehabilitation of an industrial mercury contaminated ...Dr. Abdul Rehman Khan - Rehabilitation of an industrial mercury contaminated ...
Dr. Abdul Rehman Khan - Rehabilitation of an industrial mercury contaminated ...promediakw
 
Update on ASTM Standards Influencing Property Due Diligence
Update on ASTM Standards Influencing Property Due Diligence Update on ASTM Standards Influencing Property Due Diligence
Update on ASTM Standards Influencing Property Due Diligence EDR
 
Assessing_the_effectiveness_of_WSUD_in_SEQ
Assessing_the_effectiveness_of_WSUD_in_SEQAssessing_the_effectiveness_of_WSUD_in_SEQ
Assessing_the_effectiveness_of_WSUD_in_SEQNathaniel Parker
 
Design, Permitting and Construction Considerations for Marcellus Shale Gas Co...
Design, Permitting and Construction Considerations for Marcellus Shale Gas Co...Design, Permitting and Construction Considerations for Marcellus Shale Gas Co...
Design, Permitting and Construction Considerations for Marcellus Shale Gas Co...All4 Inc.
 
Hensel, Corrigan, Helmers & Hoefs - Emissions Reductions in Southeastern MN: ...
Hensel, Corrigan, Helmers & Hoefs - Emissions Reductions in Southeastern MN: ...Hensel, Corrigan, Helmers & Hoefs - Emissions Reductions in Southeastern MN: ...
Hensel, Corrigan, Helmers & Hoefs - Emissions Reductions in Southeastern MN: ...Environmental Initiative
 
Moffett RAB: Navy Vapor Intrusion Update
Moffett RAB: Navy Vapor Intrusion UpdateMoffett RAB: Navy Vapor Intrusion Update
Moffett RAB: Navy Vapor Intrusion UpdateSteve Williams
 
Andrew Gorman resume 2015
Andrew Gorman resume 2015Andrew Gorman resume 2015
Andrew Gorman resume 2015Andrew Gorman
 
LCW Restoration Plan & EIR- Public Workshop #2
LCW Restoration Plan & EIR- Public Workshop #2LCW Restoration Plan & EIR- Public Workshop #2
LCW Restoration Plan & EIR- Public Workshop #2TidalInlfluence
 
A Regulatory Update Of Stormwater Requirements.Km
A Regulatory Update Of Stormwater Requirements.KmA Regulatory Update Of Stormwater Requirements.Km
A Regulatory Update Of Stormwater Requirements.KmKelseyMusich
 
Recent Developments in Environmental Due Diligence
Recent Developments in Environmental Due DiligenceRecent Developments in Environmental Due Diligence
Recent Developments in Environmental Due DiligenceAllen Matkins
 
Gary Merritt, Northern Star Generation LLC, “Big Yellow Taxi?…You don’t know...
Gary Merritt, Northern Star Generation LLC,  “Big Yellow Taxi?…You don’t know...Gary Merritt, Northern Star Generation LLC,  “Big Yellow Taxi?…You don’t know...
Gary Merritt, Northern Star Generation LLC, “Big Yellow Taxi?…You don’t know...Michael Hewitt, GISP
 
7200 rev1 plumbing
7200 rev1 plumbing7200 rev1 plumbing
7200 rev1 plumbingbhattbhai
 

What's hot (20)

Brad Shultz, OSMRE, “Effective Aerobic Wetland Design for Metals Polishing in...
Brad Shultz, OSMRE, “Effective Aerobic Wetland Design for Metals Polishing in...Brad Shultz, OSMRE, “Effective Aerobic Wetland Design for Metals Polishing in...
Brad Shultz, OSMRE, “Effective Aerobic Wetland Design for Metals Polishing in...
 
Doug Deason - Annual Meeting
Doug Deason - Annual MeetingDoug Deason - Annual Meeting
Doug Deason - Annual Meeting
 
Leed Water Efficiency Credits V3
Leed   Water Efficiency Credits  V3Leed   Water Efficiency Credits  V3
Leed Water Efficiency Credits V3
 
Gonzalez Resume
Gonzalez ResumeGonzalez Resume
Gonzalez Resume
 
M. pinto n8848489 project 1_presentation
M. pinto n8848489 project 1_presentationM. pinto n8848489 project 1_presentation
M. pinto n8848489 project 1_presentation
 
Gopal K - UEI Day 1 - Kochi Jan18
Gopal K - UEI Day 1 - Kochi Jan18Gopal K - UEI Day 1 - Kochi Jan18
Gopal K - UEI Day 1 - Kochi Jan18
 
Dr. Abdul Rehman Khan - Rehabilitation of an industrial mercury contaminated ...
Dr. Abdul Rehman Khan - Rehabilitation of an industrial mercury contaminated ...Dr. Abdul Rehman Khan - Rehabilitation of an industrial mercury contaminated ...
Dr. Abdul Rehman Khan - Rehabilitation of an industrial mercury contaminated ...
 
Update on ASTM Standards Influencing Property Due Diligence
Update on ASTM Standards Influencing Property Due Diligence Update on ASTM Standards Influencing Property Due Diligence
Update on ASTM Standards Influencing Property Due Diligence
 
Assessing_the_effectiveness_of_WSUD_in_SEQ
Assessing_the_effectiveness_of_WSUD_in_SEQAssessing_the_effectiveness_of_WSUD_in_SEQ
Assessing_the_effectiveness_of_WSUD_in_SEQ
 
Advocating Water Quality Improvement in Detroit
Advocating Water Quality Improvement in DetroitAdvocating Water Quality Improvement in Detroit
Advocating Water Quality Improvement in Detroit
 
Design, Permitting and Construction Considerations for Marcellus Shale Gas Co...
Design, Permitting and Construction Considerations for Marcellus Shale Gas Co...Design, Permitting and Construction Considerations for Marcellus Shale Gas Co...
Design, Permitting and Construction Considerations for Marcellus Shale Gas Co...
 
Hensel, Corrigan, Helmers & Hoefs - Emissions Reductions in Southeastern MN: ...
Hensel, Corrigan, Helmers & Hoefs - Emissions Reductions in Southeastern MN: ...Hensel, Corrigan, Helmers & Hoefs - Emissions Reductions in Southeastern MN: ...
Hensel, Corrigan, Helmers & Hoefs - Emissions Reductions in Southeastern MN: ...
 
Moffett RAB: Navy Vapor Intrusion Update
Moffett RAB: Navy Vapor Intrusion UpdateMoffett RAB: Navy Vapor Intrusion Update
Moffett RAB: Navy Vapor Intrusion Update
 
Andrew Gorman resume 2015
Andrew Gorman resume 2015Andrew Gorman resume 2015
Andrew Gorman resume 2015
 
LCW Restoration Plan & EIR- Public Workshop #2
LCW Restoration Plan & EIR- Public Workshop #2LCW Restoration Plan & EIR- Public Workshop #2
LCW Restoration Plan & EIR- Public Workshop #2
 
Brownfields Remediation
Brownfields RemediationBrownfields Remediation
Brownfields Remediation
 
A Regulatory Update Of Stormwater Requirements.Km
A Regulatory Update Of Stormwater Requirements.KmA Regulatory Update Of Stormwater Requirements.Km
A Regulatory Update Of Stormwater Requirements.Km
 
Recent Developments in Environmental Due Diligence
Recent Developments in Environmental Due DiligenceRecent Developments in Environmental Due Diligence
Recent Developments in Environmental Due Diligence
 
Gary Merritt, Northern Star Generation LLC, “Big Yellow Taxi?…You don’t know...
Gary Merritt, Northern Star Generation LLC,  “Big Yellow Taxi?…You don’t know...Gary Merritt, Northern Star Generation LLC,  “Big Yellow Taxi?…You don’t know...
Gary Merritt, Northern Star Generation LLC, “Big Yellow Taxi?…You don’t know...
 
7200 rev1 plumbing
7200 rev1 plumbing7200 rev1 plumbing
7200 rev1 plumbing
 

Similar to Lynas malaysia public communication july 13 2009 doe presentation

EIA for development projects
EIA for development projectsEIA for development projects
EIA for development projectsAnchal Garg
 
Unit V - EIA case studies pertaining to Infrastructure Projects.pptx
Unit V - EIA case studies pertaining to Infrastructure Projects.pptxUnit V - EIA case studies pertaining to Infrastructure Projects.pptx
Unit V - EIA case studies pertaining to Infrastructure Projects.pptxssuser65cc68
 
DESALINATION OF SEAWATER USING WATER HYACINTH ACTIVATED CARBON
DESALINATION OF SEAWATER USING WATER HYACINTH ACTIVATED CARBONDESALINATION OF SEAWATER USING WATER HYACINTH ACTIVATED CARBON
DESALINATION OF SEAWATER USING WATER HYACINTH ACTIVATED CARBONIRJET Journal
 
Environmental Management - Coal Mining
Environmental Management - Coal MiningEnvironmental Management - Coal Mining
Environmental Management - Coal MiningKrishna Deo Prasad
 
Esia of 132 kv mehmoodabad g.s and u.g transmission line from qayumabad g.s
Esia of 132 kv mehmoodabad g.s and u.g transmission line from qayumabad g.sEsia of 132 kv mehmoodabad g.s and u.g transmission line from qayumabad g.s
Esia of 132 kv mehmoodabad g.s and u.g transmission line from qayumabad g.szubeditufail
 
Environmental Impact Assessment of Kota Super Thermal Power Station
Environmental Impact Assessment of Kota Super Thermal Power Station Environmental Impact Assessment of Kota Super Thermal Power Station
Environmental Impact Assessment of Kota Super Thermal Power Station IJSRP Journal
 
Eiarfd2015 pce5271lokeshrakesh
Eiarfd2015 pce5271lokeshrakeshEiarfd2015 pce5271lokeshrakesh
Eiarfd2015 pce5271lokeshrakeshLokesh Saini
 
Andersen Environmental Brochure 2011
Andersen Environmental Brochure 2011Andersen Environmental Brochure 2011
Andersen Environmental Brochure 2011andersenenviro
 
Performance Evaluation of Sewage Treatment Plant in Kanpur City
Performance Evaluation of Sewage Treatment Plant in Kanpur CityPerformance Evaluation of Sewage Treatment Plant in Kanpur City
Performance Evaluation of Sewage Treatment Plant in Kanpur CityIRJET Journal
 
ENVIRONMENTAL IMPACT ASSESSMENT ON DAL LAKE SRINAGAR KASHMIR
ENVIRONMENTAL IMPACT ASSESSMENT ON DAL LAKE SRINAGAR KASHMIRENVIRONMENTAL IMPACT ASSESSMENT ON DAL LAKE SRINAGAR KASHMIR
ENVIRONMENTAL IMPACT ASSESSMENT ON DAL LAKE SRINAGAR KASHMIRIRJET Journal
 
Stormwater Monitoring - Newington Solid Waste Facility
Stormwater Monitoring - Newington Solid Waste FacilityStormwater Monitoring - Newington Solid Waste Facility
Stormwater Monitoring - Newington Solid Waste FacilityFairfax County
 

Similar to Lynas malaysia public communication july 13 2009 doe presentation (20)

15. Licensing of Large Point Source Discharges
15. Licensing of Large Point Source Discharges15. Licensing of Large Point Source Discharges
15. Licensing of Large Point Source Discharges
 
EIA for development projects
EIA for development projectsEIA for development projects
EIA for development projects
 
Unit V - EIA case studies pertaining to Infrastructure Projects.pptx
Unit V - EIA case studies pertaining to Infrastructure Projects.pptxUnit V - EIA case studies pertaining to Infrastructure Projects.pptx
Unit V - EIA case studies pertaining to Infrastructure Projects.pptx
 
DESALINATION OF SEAWATER USING WATER HYACINTH ACTIVATED CARBON
DESALINATION OF SEAWATER USING WATER HYACINTH ACTIVATED CARBONDESALINATION OF SEAWATER USING WATER HYACINTH ACTIVATED CARBON
DESALINATION OF SEAWATER USING WATER HYACINTH ACTIVATED CARBON
 
Environmental Management - Coal Mining
Environmental Management - Coal MiningEnvironmental Management - Coal Mining
Environmental Management - Coal Mining
 
Esia of 132 kv mehmoodabad g.s and u.g transmission line from qayumabad g.s
Esia of 132 kv mehmoodabad g.s and u.g transmission line from qayumabad g.sEsia of 132 kv mehmoodabad g.s and u.g transmission line from qayumabad g.s
Esia of 132 kv mehmoodabad g.s and u.g transmission line from qayumabad g.s
 
Environmental Impact Assessment of Kota Super Thermal Power Station
Environmental Impact Assessment of Kota Super Thermal Power Station Environmental Impact Assessment of Kota Super Thermal Power Station
Environmental Impact Assessment of Kota Super Thermal Power Station
 
Lead asbestos mgmt plan - ems manual
Lead   asbestos mgmt plan - ems manualLead   asbestos mgmt plan - ems manual
Lead asbestos mgmt plan - ems manual
 
resume_VISHAL_New
resume_VISHAL_Newresume_VISHAL_New
resume_VISHAL_New
 
Pollutant Threshold Industry Consultation
Pollutant Threshold Industry ConsultationPollutant Threshold Industry Consultation
Pollutant Threshold Industry Consultation
 
C0 2 ricardo_environmental
C0 2 ricardo_environmentalC0 2 ricardo_environmental
C0 2 ricardo_environmental
 
Environmental presentation ce
Environmental presentation ceEnvironmental presentation ce
Environmental presentation ce
 
Eiarfd2015 pce5271lokeshrakesh
Eiarfd2015 pce5271lokeshrakeshEiarfd2015 pce5271lokeshrakesh
Eiarfd2015 pce5271lokeshrakesh
 
AE Company Brochure
AE Company Brochure AE Company Brochure
AE Company Brochure
 
Andersen Environmental Brochure 2011
Andersen Environmental Brochure 2011Andersen Environmental Brochure 2011
Andersen Environmental Brochure 2011
 
Performance Evaluation of Sewage Treatment Plant in Kanpur City
Performance Evaluation of Sewage Treatment Plant in Kanpur CityPerformance Evaluation of Sewage Treatment Plant in Kanpur City
Performance Evaluation of Sewage Treatment Plant in Kanpur City
 
James riverpartnership2003
James riverpartnership2003James riverpartnership2003
James riverpartnership2003
 
ENVIRONMENTAL IMPACT ASSESSMENT ON DAL LAKE SRINAGAR KASHMIR
ENVIRONMENTAL IMPACT ASSESSMENT ON DAL LAKE SRINAGAR KASHMIRENVIRONMENTAL IMPACT ASSESSMENT ON DAL LAKE SRINAGAR KASHMIR
ENVIRONMENTAL IMPACT ASSESSMENT ON DAL LAKE SRINAGAR KASHMIR
 
PROJECT PPT.pptx
PROJECT PPT.pptxPROJECT PPT.pptx
PROJECT PPT.pptx
 
Stormwater Monitoring - Newington Solid Waste Facility
Stormwater Monitoring - Newington Solid Waste FacilityStormwater Monitoring - Newington Solid Waste Facility
Stormwater Monitoring - Newington Solid Waste Facility
 

More from Lynas Malaysia

Free trade? One mining firm begs to differ the australian 22 may
Free trade? One mining firm begs to differ   the australian 22 mayFree trade? One mining firm begs to differ   the australian 22 may
Free trade? One mining firm begs to differ the australian 22 mayLynas Malaysia
 
AELB mengumumkan kelulusan lesen operasi sementara untuk Loji Bahan-Bahan Maj...
AELB mengumumkan kelulusan lesen operasi sementara untuk Loji Bahan-Bahan Maj...AELB mengumumkan kelulusan lesen operasi sementara untuk Loji Bahan-Bahan Maj...
AELB mengumumkan kelulusan lesen operasi sementara untuk Loji Bahan-Bahan Maj...Lynas Malaysia
 
Lynas Receives Temporary Operating License from AELB
Lynas Receives Temporary Operating License from AELBLynas Receives Temporary Operating License from AELB
Lynas Receives Temporary Operating License from AELBLynas Malaysia
 
Ksu visits opposition false allegations 14 dec 2011
Ksu visits opposition false allegations 14 dec 2011Ksu visits opposition false allegations 14 dec 2011
Ksu visits opposition false allegations 14 dec 2011Lynas Malaysia
 
Reply letter from MP Fuziah Salleh to Nick Curtis
Reply letter from MP Fuziah Salleh to Nick CurtisReply letter from MP Fuziah Salleh to Nick Curtis
Reply letter from MP Fuziah Salleh to Nick CurtisLynas Malaysia
 
Lynas Malaysia Public Communication July 13 2009 - Nuclear Malaysia presentation
Lynas Malaysia Public Communication July 13 2009 - Nuclear Malaysia presentationLynas Malaysia Public Communication July 13 2009 - Nuclear Malaysia presentation
Lynas Malaysia Public Communication July 13 2009 - Nuclear Malaysia presentationLynas Malaysia
 
Lynas malaysia public communication july 13 2009 aelb presentation
Lynas malaysia public communication july 13 2009  aelb presentationLynas malaysia public communication july 13 2009  aelb presentation
Lynas malaysia public communication july 13 2009 aelb presentationLynas Malaysia
 
Lynas malaysia public communication july 13 2009 pknp presentation
Lynas malaysia public communication july 13 2009  pknp presentationLynas malaysia public communication july 13 2009  pknp presentation
Lynas malaysia public communication july 13 2009 pknp presentationLynas Malaysia
 
Lynas background information
Lynas background informationLynas background information
Lynas background informationLynas Malaysia
 
Lynas Concentration Plant
Lynas Concentration PlantLynas Concentration Plant
Lynas Concentration PlantLynas Malaysia
 
Public Briefing on Lynas Malaysia
Public Briefing on Lynas MalaysiaPublic Briefing on Lynas Malaysia
Public Briefing on Lynas MalaysiaLynas Malaysia
 

More from Lynas Malaysia (14)

Free trade? One mining firm begs to differ the australian 22 may
Free trade? One mining firm begs to differ   the australian 22 mayFree trade? One mining firm begs to differ   the australian 22 may
Free trade? One mining firm begs to differ the australian 22 may
 
AELB mengumumkan kelulusan lesen operasi sementara untuk Loji Bahan-Bahan Maj...
AELB mengumumkan kelulusan lesen operasi sementara untuk Loji Bahan-Bahan Maj...AELB mengumumkan kelulusan lesen operasi sementara untuk Loji Bahan-Bahan Maj...
AELB mengumumkan kelulusan lesen operasi sementara untuk Loji Bahan-Bahan Maj...
 
Lynas Receives Temporary Operating License from AELB
Lynas Receives Temporary Operating License from AELBLynas Receives Temporary Operating License from AELB
Lynas Receives Temporary Operating License from AELB
 
Ksu visits opposition false allegations 14 dec 2011
Ksu visits opposition false allegations 14 dec 2011Ksu visits opposition false allegations 14 dec 2011
Ksu visits opposition false allegations 14 dec 2011
 
Lynas Dispels Myths
Lynas Dispels Myths Lynas Dispels Myths
Lynas Dispels Myths
 
Lynas JV announcement
Lynas JV announcementLynas JV announcement
Lynas JV announcement
 
Reply letter from MP Fuziah Salleh to Nick Curtis
Reply letter from MP Fuziah Salleh to Nick CurtisReply letter from MP Fuziah Salleh to Nick Curtis
Reply letter from MP Fuziah Salleh to Nick Curtis
 
Lynas Malaysia Public Communication July 13 2009 - Nuclear Malaysia presentation
Lynas Malaysia Public Communication July 13 2009 - Nuclear Malaysia presentationLynas Malaysia Public Communication July 13 2009 - Nuclear Malaysia presentation
Lynas Malaysia Public Communication July 13 2009 - Nuclear Malaysia presentation
 
Lynas malaysia public communication july 13 2009 aelb presentation
Lynas malaysia public communication july 13 2009  aelb presentationLynas malaysia public communication july 13 2009  aelb presentation
Lynas malaysia public communication july 13 2009 aelb presentation
 
Lynas malaysia public communication july 13 2009 pknp presentation
Lynas malaysia public communication july 13 2009  pknp presentationLynas malaysia public communication july 13 2009  pknp presentation
Lynas malaysia public communication july 13 2009 pknp presentation
 
LAMP Refinery Process
LAMP Refinery ProcessLAMP Refinery Process
LAMP Refinery Process
 
Lynas background information
Lynas background informationLynas background information
Lynas background information
 
Lynas Concentration Plant
Lynas Concentration PlantLynas Concentration Plant
Lynas Concentration Plant
 
Public Briefing on Lynas Malaysia
Public Briefing on Lynas MalaysiaPublic Briefing on Lynas Malaysia
Public Briefing on Lynas Malaysia
 

Lynas malaysia public communication july 13 2009 doe presentation

  • 1. PUBLIC BRIEFING ON LYNAS LANTHANIDES PROJECT PRESENTER : PUAN AZURI AZIZAH BT. HJ. SAEDON DEPARTMENT OF ENVIRONMENT PAHANG TINGKAT 4, BANGUNAN ASIA LIFE JALAN TELUK SISEK 25662 KUANTAN
  • 2. Department of Environment Ministry of Natural Resources and Environment Other government Department of Other government agencies Environment (DOE) agencies 1975 - Environment Division 1983 - Department of Environment (DOE) -2-
  • 3. Roles of Department of Environment (DOE) To administer and enforce the Environmental Quality Act, 1974 : Prevention, abatement and control of pollution and enhancement of the environment There are 34 subsidiary legislations under the Act -3-
  • 4. Lynas must comply to the following Act & Regulations Environmental Quality Act 1974 : Environmental Impact Assessment (EIA) report Quantitative Risk Assessment (QRA) report Guidelines for Prevention and Control of Soil Erosion and Siltation in Malaysia , October 1996. Environmental Quality (Sewage, and Industrial Effluents) Regulations, 1979 Environmental Quality (Clean Air) Regulations,1978 Environmental Quality (Scheduled Wastes) Regulations, 2005 Planning Guidelines for Environmental Noise Limit and Controls, 2004 -4-
  • 5. Conditions of Approval for Lynas EIA and QRA prepared by registered environmental consultant Proper and designated drainage system for the Residue Storage Facilities (RSF) Safety and Emergency control AELB’s approval on monitoring, management and disposal of radioactive containing materials Chemical and scheduled waste management Solid waste management Environmental management plan (EMP) Control and monitoring of : Air quality - soil condition - Noise Water quality including underground water -5-
  • 6. Requirements that Lynas must comply and monitored by DOE Suspended solid less than 100 mg/l from the silt trap discharge during construction Water quality monitoring report on 30 parameters upstream and downstream of Sungai Balok 4 borewells for underground water quality monitoring Ambient Air Quality monitoring of parameters CO2, CO, NO2, NO, SO2, HF, H2SO4, PM10, and TSP Noise monitoring at four (4) stations Discharge effluent quality report from the final discharge point Stack emission sampling to comply Standard C, Clean Air Regulations, 1978 and AELB’s standards. Compliance report Environment audit report -6-
  • 7. Lynas Project : AIR How will Lynas ensure its Air Emissions meet DOE requirements? Lynas will install waste gas treatment systems for the removal of sulfuric acid and sulfur dioxide It is a five-stage waste gas scrubbing system Lynas also has an emergency scrubbing system to ensure air emission meet DOE requirements at all times Air Quality Modelling has been completed -7-
  • 8. Lynas Project : WATER How will Lynas ensure its Industrial Effluents meet DOE requirements? Lynas will install a 2-stage waste water treatment system High Density Sludge Neutralization to neutralize acids and remove metals Industrial effluent treatment system (IETS), an activated sludge bio-treatment To treat process water to reduce BOD and COD IE discharges to comply to Standard B of Regulation 8(1)(b), Environmental Quality (Sewage, and Industrial Effluents) Regulations, 1979 and AELB’s standards Lynas will install an independent storm water system To ensure Storm water will not be contaminated by process water Waste water from the Water Leached Process is recycled back to the process. -8-
  • 9. Conclusion DOE approved the Lynas Project after a detailed review of the EIA and QRA submitted by Environ in Jan 2008. Approval was granted with conditions in Feb 2008. DOE separately approve the detailed design of key pollution control equipment prior to installation, and for the Lynas Project this includes the waste water treatment plant and the waste gas treatment plant. After EMP approval on Dec 2008, three site visits have been conducted by DOE; construction works complied to EIA conditions. DOE, as the regulator, will ensure that Lynas operates consistent with the act and regulations so that the impact to the environment is minimised. -9-
  • 11. Water Quality Monitoring W7 W6 W5 W4 W3 W2 W1 -11-
  • 12. Underground Water Quality Monitoring S3 S1 S7 S2 S4 S6 S5 -12-
  • 13. Ambient Air Quality Monitoring A3 A1 A2 A4 -13-
  • 14. Noise Monitoring N3 N1 N2 N4 -14-